Davey Mackison & Reid
Construction Consultants
Healthcare & Medical
Methodist Hospitals - Southlake Campus
Addition of a 30 bed extension to the existing Southlake Campus, in Merrillville, IN. The project required a design response, schedule and plan for coordinating the on-site construction showing how the disruption to existing operations would be mitigated. The estimate and selection of our team was based on cost and presentation.
Danbury Hospital
Addition of an MRI machine to the Radiology Wing of Danbury Hospital, involving the demolition and remodeling of existing space.
VA Medical Center Radiology Renovations
An approximate $3M Cost Estimate analyzing the renovation costs of Five (5) distinct areas of development for the veterans Affairs Hospital. Sub-projects consist of the following:
We work equally well with Lawyers, Owners or Contractors.
• Area A - MRI/CT Suite
$1,000,000, 4100 sf renovation modifying MEP, Fire Suppression and the addition
of a Quench Vent System. Excluded equipment costs.
• Area B - Radiation/Oncology
$500,000, 3000 sf Renovation Modifying MEP, Fire Suppression and Architectural
Finishes.
• Area D - General Radiation/Ultrasound
$950,000, 7,000 sf Renovation Modifying MEP, Fire Suppression and Architectural
Finishes.
• Area D - Nuclear Medicine
$400,000, 2,800 sf Renovation Modifying MEP, Fire Suppression and Architectural
Finishes.
• Area E - Basement Architectural Finishes Renovation
$20,000, 700 sf Renovation Modifying Architectural Finishes